Closures begin Friday as 60 Freeway is repaved in Industry

Dubbed the Summer Slam, various sections of the 60 Freeway in the City of Industry will close from 10 p.m. Friday to at least 5 a.m. Monday on four weekends in July and August for repaving.

The first closure, July 12-15, will see three westbound lanes closed between Fullerton Road and Nogales Street. The second, July 26-29, is for the final two westbound lanes. On Aug. 9-12, three eastbound lanes will close. The job is scheduled to end Aug. 23-26 for the final two eastbound lanes.

The road won’t be completely closed, but drivers are advised to use alternate routes.